Caltrans plans major roadwork through July 8

NORTH COAST – Caltrans reports that the following road projects will be taking place around Lake County during the coming week.


Included are Mendocino County projects that may impact Lake County commuters.


Caltrans will suspend work on Northern California highways Friday, July 2, through Monday, July 5, in observance of the Independence Day weekend. However, due to unforeseen circumstances, it may be necessary for Caltrans Maintenance forces to respond to emergency situations.


LAKE COUNTY


Highway 20


– The Habematolel Pomo of Upper Lake have been granted a Caltrans Encroachment Permit for installation of light poles near Government Street beginning Tuesday, July 6. Work hours are 8 a.m. to 4 p.m., weekdays. Traffic will be restricted to one lane in each direction of travel. Motorists may experience minor traffic slowdowns.


– Caltrans will perform routine maintenance from Ogden Road to Hillside Lane. Work hours are 7 a.m. to 3:30 p.m., Tuesday through Friday. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.


Highway 29


– Caltrans will perform routine maintenance from Hartman Road to 0.3 mile south of Hofacker Lane. Work hours are 7:30 a.m. to 3:30 p.m., Tuesday through Friday. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.


Highway 281


– North Bay Construction of Petaluma has been granted a Caltrans Encroachment Permit for paving on Soda Bay Road. Work hours are 7 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.


MENDOCINO COUNTY


Highway 1


– The city of Point Arena has been issued a Caltrans Encroachment permit to hold the annual Independence Day Parade between Iverson Lane and Main Street in Point Arena on Sunday, July 4. A road closure will be in effect from 11:30 a.m. to 1:30 p.m. Motorists are advised to use an alternate route.


– Paving from 0.1 mile north of Navarro Ridge Road to Woodstock Drive will continue. Work hours are 7:30 a.m. to 3:30 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays. Contractor – Granite Construction of Ukiah.


– The Mendocino Coast Chamber of Commerce has been granted a Caltrans Encroachment Permit to hold the July 4 fireworks from the junction of Highways 1 and 20 to South Street on Saturday, July 3, from 8 p.m. to 11 p.m. Turns onto Ocean View Drive will be restricted. Motorists may experience minor traffic slowdowns.


– PG&E of Ukiah has been granted a Caltrans Encroachment Permit for an aerial crossing at Airport Road on Thursday, July 8. Work hours are 10 a.m. to 10:30 a.m. Intermittent full road closures will be in effect. Motorists should anticipate five-minute delays.


Highway 101


– A culvert repair project form Waterplant Road to the Haehl Overhead Bridge will continue. Work hours are 8 p.m. to 3 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Granite Construction of Ukiah.


– The city of Willits has been granted a Caltrans Encroachment Permit to hold the Frontier Days Parade between Franklin Avenue and Commercial Street on Sunday, July 4, from 9 a.m. to 1 p.m. A full road closure will be in effect. A detour will be provided.


Highway 162


– A bridge widening project at Outlet Creek Bridge will continue. Work hours are 7 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 15-minute delays. Contractor – Viking Construction Co. Inc. of Rancho Cordova.


Highway 222


– Replacement of the Russian River Bridge will continue. Work hours are 7 a.m. to 5 p.m., weekdays. One-way traffic control with a temporary signal will be in effect 24 hours per day, seven days per week. Motorists should anticipate 15-minute delays during work hours and five-minute delays at other times. Contractor – CC Myers of Rancho Cordova.


– Rogina Water Co. of Talmage has been granted a Caltrans Encroachment Permit to install a water line from Sandford Ranch Road to Talmage Court. Work hours are 7 a.m. to 5 p.m., weekdays. Intermittent one-way traffic control will be in effect. Motorists should anticipate five-minute delays.


Highway 253


– Construction of a retaining wall from Singley Cattlepass to the Soda Creek Bridge will continue. Work hours are 7 a.m. to 5 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays. Contractor – Mendocino Construction Services of Willits.


– A bridge widening project at Soda Creek Bridge will continue. Work hours are 7 a.m. to 5 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Viking Construction Co. Inc. of Rancho Cordova.


For information pertaining to emergency roadwork or for updates to scheduled roadwork, please contact the California Highway Information Network (CHIN) at 1-800-GAS-ROAD (1-800-427-7623).

Upcoming Calendar

14Oct
14Oct
10.14.2024
Columbus Day
31Oct
10.31.2024
Halloween
3Nov
11Nov
11.11.2024
Veterans Day
28Nov
11.28.2024
Thanksgiving Day
29Nov
24Dec
12.24.2024
Christmas Eve

Mini Calendar

loader

LCNews

Award winning journalism on the shores of Clear Lake. 

 

Newsletter

Enter your email here to make sure you get the daily headlines.

You'll receive one daily headline email and breaking news alerts.
No spam.
Cookies!

lakeconews.com uses cookies for statistical information and to improve the site.

// Infolinks